JCT Construction contracts and the question of joint names or composite construction insurance

Posted on: August 21st, 2024 by Hugh Dineen-Lees

Construction projects are necessarily complex risk structures in themselves, relating to a mix of workmanship, design and the particulars of the construction process. Parties to a construction project will often extend beyond those commissioning the work (the employer) and carrying it out (the contractor). It is often more likely that the parties will include architects, engineers, project managers, numerous subcontractors and suppliers and – via collateral warranties – future purchasers, tenants and funders. All of these actors can contribute to loss or damage and, ultimately, legal liabilities.

This contractual complexity requires construction insurance arrangements which match the risks facing each party and the nature of their interest in the project. It is sensible therefore to obtain insurance advice to ensure the correct policy terms – joint names or composite insured – are in place before works begin.

What is joint names construction insurance?

Joint names is an insurance policy extension that covers the contractual responsibilities of both the employer and the contractor. It applies to new build and refurbishment contracts where there is a requirement to name parties on a construction insurance policy that will cover the contract works and any existing structure as under the standard terms JCT suite of contracts.

A joint names extension has the following likely characteristics:

  • removes the need for each party to take out separate policies covering their own responsibilities and therefore eliminate the risk/cost of duplicated insurance arrangements;
  • ensures that the named parties – e.g., employer and contractor – cannot claim against one another; and
  • makes it impossible for one party to cancel the policy without notifying one or all of the other named parties.

Joint names works when the contracted parties’ interests are aligned – as are those of the employer and contractor who are both going to be looking for the works to be completed on time, on budget and to the agreed contractual standard.

What is composite insured construction insurance?

Composite insured is different and is often applied where the project parties have a separate and individual interest in the works. The most obvious example is that of a funder’s interest in a construction project which, unlike the employer or contractor, has as its primary interest the return of its loan facility and interest. This may or may not be separate from the successful completion of the works.

A composite insured extension is generally written on a bespoke basis to reflect the different interests of the various project parties so as to protect their individual interests – this can be achieved by the inclusion for instance of first loss payee provisions which generally seek to cover the original loan plus interest.

This risk cover is obviously different to one based on a joint names extension which just notes a funder’s interest in a project.

In brief: the difference between joint named and composite insured

  • Both joint names and composite insured are insurance policy extensions applicable under JCT contracts standard terms.
  • Joint names extensions are most commonly applicable where the insured parties have similar undivided interests in the project.
  • Composite insured extensions are more applicable where one or more parties have their own interests, separate from the other parties.

The insurance market is a market, which changes on a daily basis as to what risks it will accept, on what terms and at what cost.

Construction professionals – including lawyers, contractors, funders and others need to work together as closely and openly as possible with brokers and underwriters in order to find the best risk cover solution for a project. The preparation and analysis of risks will lead to the actual insurance contract terms – almost certainly by way of addendum or changes to the standard terms, This is where the assistance of lawyers will most likely be needed.

If you would like further information on construction contracts and the types of insurance that can be used to cover them, please contact a member of our Construction team.

Collateral warranties – a turning point?

Posted on: July 18th, 2024 by Natasha Cox

On 9 July 2024, the Supreme Court gave judgment in a case which raised the question of whether the beneficiary of a collateral warranty had the right to refer disputes arising from the warranty to adjudication.

If you would like to know more about this judgment, please download the attached PDF.

If you would like some advice on the potential impacts of this ruling. please get in touch with Matthew Needham-Laing.

2024.07.18 Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP collateral warranties

Landlord and tenant works – Construction Industry Scheme payments now made simpler

Posted on: June 13th, 2024 by Natasha Cox

In brief:

Regulations were introduced in April of this year which removed the uncertainty and complexity on which payments made by commercial landlords to tenants are covered by the Construction Industry Scheme (CIS). As a result,  the majority of such payments will now fall outside the scope of the CIS and the requirement for deductions as advance payments towards a sub-contractor’s tax and National insurance to HMRC.

The pre-April 2024 rules created a cumbersome legal and administrative obligation and the removal of these compliance burdens must be welcomed.

Legislation

The Income Tax (Construction Industry Scheme) (Amendment) Regulations 2024 (SI 2024/308)  introduced in April 2024 added a new Regulation 20A to the main CIS regulations which specify that payments made by a landlord to a tenant for construction operations in connection with a lease or agreement for lease are not contract payments and are, therefore, outside the scope of the CIS.

To fall within the scope of this exclusion, payments must meet the following conditions:

  • The payment is made by or on behalf of a landlord;
  • The payment is received by a tenant or prospective tenant (tenants include sub-tenants);
  • The payment is for construction operations agreed in connection with a lease or agreement for lease;
  • The tenant that occupies or will occupy the property will carry out the construction works themselves or contract with a third party to undertake the work; and
  • The payment must be for construction operations relating to works intended primarily for the benefit and use of the tenant that occupies or will occupy the property under the lease.

The definition of ‘landlord’ includes a person with the legal or beneficial ownership of the property, who granted the lease or who will grant the lease.

What does this mean?

Under the pre-April 2024 rules, and prior to entering into any agreement relevant to the construction operations, both the landlord and tenant were required to take legal and taxation advice in order to jointly agree and document that any payments from the landlord to the tenant regarding such construction works either fell within the exclusion for ‘reverse premiums’ in Regulation 20 of the main CIS regulations so that they fell outside the scope of the CIS – or they did not and deductions would need to be made. 

Although contributions made by a landlord towards the tenant’s own fit out works were easier to assess, it was far more difficult where a contribution was being made towards the tenant undertaking Category A fit out works. This led to some landlords being more ‘careful’ in requiring the operation of the CIS on such contributions. Tenants were being asked to take on the added cost of CIS deductions –  as well as the added administrative and cash flow burdens of having to reclaim the amounts deducted. 

The new exclusion under Regulation 20A should lead to most payments by landlords to tenants (or prospective tenants) for construction operations being defined as outside of the scope of the CIS. However,, the implications of Regulation 20A do need to be fully understood.  Most notably,is the requirement that the landlord’s payments must be for construction works intended primarily for the benefit and use of the tenant. This means that any payment which relates to works outside the property occupied by the tenant is likely to fall outside the new exclusion and will therefore remain within the scope of the CIS.

As a reminder…

The new regulations do not affect the application of the CIS to payments by tenants to landlords for construction operations. Take an example where where the landlord has agreed to undertake the tenant’s own fit out works., While these payments will continue to usually fall outside the scope of the CIS, if the tenant will be sub-letting part or the whole of the property or they are registered with HMRC as a so-called ‘contractor’, the CIS deductions would apply in accordance with  Regulation 24 of the main CIS regulations for payments in respect of property used for the purposes of the business of the tenant or another company in the same group.

If you need any advice on the Construction Industry Scheme or any other aspects of construction law, please contact our team of experts Anne Wright and Tom Pemberton.

 

JCT Design and Build Contract 2024 – the first in the next generation of building contracts

Posted on: May 17th, 2024 by Natasha Cox

The JCT 2024 Design and Build Contract (JCT DB 2024) represents the first major update of the JCT forms since 2016.  The underlying structure has not changed, but the JCT has taken the opportunity for a comprehensive refresh of the JCT DB main contract and sub-contract forms.

A number of changes have been made, including the following:

New Relevant Events:  For the first time, JCT DB 2024 expressly entitles the Contractor to an extension of time if practical completion is delayed by:

  • a shortage of labour, services or materials caused by an epidemic which first occurs after the Base Date or whose effects change after the Base Date – this is the JCT’s considered response to the Covid-19 pandemic; or
  • a change in primary or secondary legislation or in guidance published by the government or other specified bodies which affects the execution of the Works – this would, for example, capture guidance by the Construction Leadership Council which is not legally binding.

While the principles seem fair, the new Relevant Events are broad in scope and we anticipate that many employers will seek to exclude them or limit their scope by making appropriate amendments. 

New optional Relevant Matters:  To complement each of the new Relevant Events noted above, there is an option in the Contract Particulars for an equivalent Relevant Matter. This would entitle the Contractor to recover the loss and/or expense it as a result of these events.  

We expect that a compromise position will be agreed in many cases allowing the new Relevant Events to apply (albeit perhaps with amendments to limit their scope), but not the optional Relevant Matters.

Termination:  If the relevant events/matters described above cause the works (or substantially the whole of the uncompleted works) to be suspended for a longer period than that identified in the Contract Particulars (the default period being two months), this is potentially grounds for termination by either party.  It is safe to assume that, had this provision been included in the JCT 2016 suite, the consequences of the Covid-19 pandemic would have been much harder for developers and their funders to manage.

Other changes have been made which impact on the parties’ rights to terminate, including the extension of the definition of insolvency. Changes have also been made to the provisions relating to payment on termination, reflecting the not so recent Construction Act notice requirements.

Limitation of the Contractor’s design liability: clause 2.17 has been comprehensively redrafted to make it clear that the Contractor has no greater duty in relation to design (to the extent permitted by the Statutory Requirements) than to exercise reasonable skill and care.   To drive the point home, there is an express exclusion of any obligation that the Contractor’s design must be fit for purpose.  While this was undoubtedly the intention behind the 2016 edition, employers and their advisory teams will no doubt look to close the gap between ‘reasonable skill and care’ and fitness for purpose without losing the benefit of the Contractor’s PI insurance which will not cover unqualified fitness for purpose liability.

Extension of time and liquidated damages:  Detailed changes have been made to the liquidated damages regime (reflecting recent case-law) and the timescales which apply to the extension of time procedure. 

Other changes: Provisions relating to collaborative working, sustainable development and environmental considerations, and the notification and negotiation of disputes have now been elevated into the core Articles and Conditions.  These were previously optional supplemental provisions so these changes represent an evolution of the JCT form rather than being radical changes.  

Various other detailed changes have been made and we recommend that users of the form purchase the tracked change versions published by the JCT to accompany the new forms which shows the changes in redline.

Template schedules of amendments need to be updated to address the changes in the JCT DB 2024 forms.

At Lawrence Stephens, our Construction & Development Finance team can advise on how best to navigate and use this new suite of contracts. 

Please contact Tom Pemberton if you have any questions regarding your project or the JCT forms.

Lawrence Stephens acts for Gibson on new Gibson Garage opening

Posted on: February 23rd, 2024 by Maverick Freedlander

We are delighted to share that Lawrence Stephens assisted Gibson, the world-famous guitar manufacturer, in the opening of its new retail concept, Gibson Garage, the first outside of Nashville on Eastcastle Street, in the heart of London.

Director and Head of Commercial Real Estate, Danny Schwarz, handled the leasing aspects. Tom Pemberton, Director in the Construction and Development Finance department, facilitated the construction element.

Lawrence Stephens has acted for Gibson for over 15 years and oversaw the move of its showroom from Rathbone Street to Eastcastle Street, which has been in the making for over two years, with the official opening taking place on 24 February. We are very excited to continue to be part of the Gibson journey.

Click here to learn more about the Gibson Garage London.

Anne Wright discusses professional indemnity insurance, development finance and what to look for – and action

Posted on: February 2nd, 2023 by AlexT

Consultant Anne Wright offers some guidance to lenders on what to look out for in respect of professional indemnity insurance from their borrower’s professional and construction teams.

It will be of no surprise that since 2018 the insurance market has hardened across most lines, with increased premiums and market capacity dwindling.

The insurance market is cyclical, however, and additional economic factors have undoubtedly affected this, such as the vast number of claims following Grenfell in 2017 and high number of insolvencies during the pandemic. It is reported that the UK PII market has approximately halved, and some insurers have withdrawn from the market altogether.

Key risks are becoming increasingly difficult to place for everyone.

In the construction industry, it is now common to find that contractors and professional consultants do not hold (or are struggling to obtain) professional indemnity insurance (PII) at the level and on the terms that either were originally negotiated and agreed with their employers and employers’ funders, or are simply not now obtainable at the outset of a development financing.

Insurers are issuing PII policies that are subject to greater exclusions and/or sub-limits in relation to (in particular) combustibility cladding and fire-safety claims. The fact that PII coverage is being restricted at a time when contractors and professional consultants need it the most is concerning. In some cases, it may lead to insolvency, as fire and cladding claims are high value – combined with the fact that larger contractors in particular, are more likely to face more than one claim in respect of their projects at any given time.

Given the current economic constraints impacting the construction industry, even greater scrutiny is needed at the initial stage of a development financing by all lender professionals.

Notwithstanding the PII market and other economic factors facing the construction industry, there are some practical steps that can be considered by lenders and borrowers to better protect against these risks:

  • Consider instructing a greater in-depth enquiry into the financial standing of contractors and key designer professional team tenderers, prior to any offer or lending facility is awarded. In recent more economically stable years, the use of outside investigation agencies has been less frequent, but these agencies should perhaps be considered again and more widely, as a prerequisite to an offer of finance.
  • Monitoring Surveyors appointed by lenders should require evidence of PII levels and terms as soon as instructed and be asked to comment on whether the same are appropriate for the project as against what is available in the market – and from whom. Due diligence conducted either in house or by external lawyers should not only ensure that each project participant carries the correct level of PII by reference to broker’s letters or certificates, but also that the same are actually “on foot” and live, and that it has not either initially or over time been varied by endorsement and/or excluded risks.
  • Insurances underwritten outside the UK market are also being offered in the alternative by professional consultants and contractors. It will be necessary to verify therefore whether the same is acceptable as a matter of jurisdiction and whether it is possible to pursue a claim in the English courts.
  • It is crucial to make sure provision is made in the construction documentation for early notice of changes in coverage to be given by the project participants to the lender’s Monitoring Surveyor so that action can be taken to limit any potential risk gap as soon as it is made known either with the assistance of the employer borrower’s own insurers or by assistance being given as to what might alternatively be available in the market. Contractor and Professional Team Collateral Warranties in favour of the lender are now more important than ever and should be prepared and executed carefully by reference to a market standard principle agreement of which it is collateral.
  • The terms of both the principle agreements and collateral warranties should be considered in light of what might be requested for inclusion of a “net contribution” provision. In the event that the employer borrower has defects claim against an under-insured or non-insured contractor and/or professional consultant the employer – and necessarily the lender – may be able to spread its risk by joining those who may be responsible (consultants, subcontractors, design consultants) to the claim. Net contribution provisions limit this more general law of “contributory negligence” in such circumstances and should therefore be resisted.
  • Parent Company Guarantees with an appropriately long liability could potentially come to the rescue too – suggest that one is asked for if available. Performance Guarantees could also be considered, although they are of limited use as the UK market rarely provides guarantee cover on an on-demand basis leading to the employer/lender waiting a very long time to have its claim even considered.
  • Lastly, it may be worthwhile exploring whether “decennial” (ten-year latent defects) insurance can be taken out with an insurance broker. This needs to be thought about at the very outset, however, and is generally restricted to new developments or infrastructure projects.

It is important to remember that PII does not cover insolvency or poor workmanship and even if adequate PII is in place it will only covers a claim for negligent professional services provided to the employer. PII is not a solution for all things that may go wrong on a project therefore but increasingly lenders are requiring to place it increased reliance on this type of insurance.